Evidence, assumptions, and a reproducible model
From a gigawatt to the things it takes.
This is an investigation of a hypothetical data centre with one gigawatt of commissioned IT load. Each run adds a layer: the plant, its equipment, material evidence, and finally an equipment material balance.
The research trail
- RUN 01
Establish the physical evidence
Gather sources and trace claims about power, cooling, equipment and material flows. Keep assumptions separate from sourced observations.
Read the findings → - RUN 01.5
Specify the reference plant
Define the load, design conditions, architecture, power and heat ledger, and equipment quantities. These remain the inherited physical reference for the site.
Read the findings → - RUN 02
Reconcile scoped materials
Connect equipment quantities to component evidence. Preserve open scopes and avoid treating unknown material content as zero.
Read the findings → - RUN 03
Deepen the forensics
Examine product documents, material fractions and engineering bounds. These scoped records remain available separately from the Run 04 estimates.
Read the findings → - RUN 04
Estimate and reconcile
Build an explicit equipment/material scenario from the retained findings and source records. Export low, base and high cases, document parameters and compare every available historical endpoint. Use the comparison records to understand differences between model versions.
Read the findings →
How to read the results
- Low / base / high are joint design cases, not confidence intervals or measured bounds. The base case is a scenario, not a certified bill of materials.
- Coverage is partial. The included equipment scopes do not close the entire campus inventory. Civil works, offsite infrastructure and other excluded or unresolved scopes are not silently counted as zero.
- Material categories have boundaries. Lithium is a nested constituent; ferrous components must not be added again to their aggregate. Follow the generated scope and accounting notes.
- Alternatives are scoped. A conductor substitution changes the stated modeled components, not every cable or transformer across the plant.
- Industry costs and lead times are context. They are not outputs or validation of the MBI material model.
Why 428 and 642 transformers?
The reference design has 428 IT step-down transformers plus 214 facility step-down transformers: 642 step-down units in total. The 24 upstream high-voltage transformers are a separate class. Transformers inside PDUs are also outside this step-down subtotal. The illustrated bricks represent classes, not one brick per physical unit.
Audit the evidence
These public copies preserve the selected research records and include source hashes. Historical reports describe their original run, while the active site uses Run 04. The full development repository remains private.
- Run 04 method
- Assumptions and model notes
- Explicit model parameters
- Generated results
- Coverage and exclusions
- Provenance
- Historical comparison
- Review and validation
- Reproduction script (requires repository dependencies)
The former Run 01.5 protocol link now leads here, covering the full Run 01–04 process. For the original protocol, see the archived Run 01.5 protocol.