Mass Balance of Intelligence: Run 01.5 findings
Snapshot SNAP-RUN015 · evidence/design date 5 October 2026 · compute vintage 2026-Q4 · PLANT-GB300-1GW-2026Q4-A implements CFG-GB300-2026Q4.
Run 01.5 supplies the missing reference plant: a modular, conditional design connecting the preserved 1 GW compute configuration to a reproducible equipment BOM. Reference Plant 01 uses 107 complete facility blocks, each provisioned for 9.431579 MW IT. Its selected summer operating point requires approximately 1.392 GW at the B2 facility boundary, compared with Run 00's conditional 1.20 GW. Annual bottom-up PUE and electricity remain unknown. Product qualification, complete material composition and procurement allocation remain open; this is a conceptual engineering reference, not a commissioned project or a universal equipment-per-GW coefficient.
The object chain is compute configuration → reference plant → equipment BOM → material BOM. The plant configuration (repository-only reference), first-class assumptions (repository-only reference) and equipment BOM (repository-only reference) extend the existing Source → Claim → Ledger instrument. They preserve its provenance, snapshots, historical records and Accounting Standard v0.1. See DESIGN_DECISIONS.md (repository-only reference) for the engineering rationale and REFERENCE_PLANT_SENSITIVITIES.md (repository-only reference) for the five largest later scenario candidates.
1. Preflight and preserved compute
The latest upstream repository was read before design work. The README, Accounting Standard v0.1, both prior findings, standard changelog, unknowns, source/claim registers, common ledger, configurations, conflicts, calculations, schemas and tests were inspected. The entire inherited suite passed 118 tests. The preflight record (repository-only reference) freezes upstream commit 6e623d739bdc793d0f4c64ce48ed39ea0e490655, original entities, file hashes and both historical balances.
The Run 00 central case reproduces without changing its 140 kW rack input, 5% extra-IT share, 1 GW IT denominator, PUE 1.20 or 90% load factor. Run 01 extends the nested shelf/PSU/die inventory without revising that denominator.
| Preserved central quantity | Value | Interpretation |
|---|---|---|
| Commissioned IT electrical requirement | 1 GW | Requirement at the server/IT boundary; no operating asset asserted |
| GB300 NVL72 rack equivalents | 6785.714286 | Fractional normalized inventory, not a purchased rack count |
| B300 accelerators | 488571.428571 | 72 per compute-rack equivalent |
| Grace CPUs | 244285.714286 | 36 per rack equivalent |
| Compute trays | 122142.857143 | 18 per rack equivalent |
| NVLink switch trays | 61071.428571 | 9 per rack equivalent |
| ConnectX-8 NICs | 488571.428571 | Four per compute tray |
| Physical HBM | 140708571.428571 manufacturer GB | Manufacturer capacity labels; not software-visible capacity |
| Power shelves | 54285.714286 | Eight per rack equivalent, preserved B1 |
| PSU modules | 325714.285714 | Six per shelf, nested within the shelves |
| Embedded GPU logic dies | 977142.857143 | Two per accelerator; not wafer starts |
| Steady IT-origin heat | Approximately 1 GWth | Preserved local heat approximation |
| Legacy facility input / annual electricity | 1.20 GW / 9.4608 TWh/year | Historical conditional PUE/load-factor calculation |
No empirical discrepancy required a compute revision. The unresolved Supermicro shelf/rack usable-power conflict remains visible. Plant transfer paths do not resolve accepted 140 kW rack failover or turn fractional inventory into additional populated racks.
2. Selected design basis and explicit adaptation
The architecture comparison (repository-only reference) examines three contemporary GB300 architecture families: Vertiv RD030, Schneider Electric's GB300/Mission Control reference designs and NVIDIA DGX GB300 SuperPOD. The selected Supermicro rack documentation supplies the actual rack interface. RD030 is selected because its complete inspected OEM diagram provides the strongest connected electrical/cooling equipment table and subsystem redundancy basis. Schneider's primary release supports liquid-to- liquid CDUs, high-temperature chillers and controls, but native detailed design downloads could not be inspected. NVIDIA provides strong compute/network and hybrid-cooling guidance rather than a complete facility BOM. Neither is silently spliced into RD030.
RD030's DGX 142 kW compute racks, 64 support racks at 14 kW and 9.984 MW total differ from the fixed Supermicro central case. Reference Plant 01 retains four 16-compute-rack PODs but adapts loading, voltage and distribution. It adds dual-input static transfer switches to retain all shelf feeds after an upstream IT train failure. It selects campus transformers, battery banks, standby generation, facility transfer paths, a climate-rated chiller proxy, larger residual-air provision and thermal buffering where RD030 is incomplete or cannot transfer safely.
| Classification | Meaning in this run | Example |
|---|---|---|
| OBSERVED | Directly evidenced report/specification, with source limitations | Trinergy 2 MW/2 MVA 480 V rating; Li5 LFP cabinet specification |
| DERIVED | Reproducible arithmetic with retained parents and design links | 107 blocks; 856 IT UPS units; 741 MWth liquid heat |
| SELECTED DESIGN ASSUMPTION | An explicit engineering choice among valid designs | Four-to-three IT trains; 78% Supermicro-rack liquid capture; 35°C design point |
| PROXY | Comparable product/system with an explicit mismatch | FH3145 for RD030 FF3145; exact 480 V 4 MW diesel class qualification |
| UNKNOWN | Insufficient evidence or accepted design specification | Annual COP, complete elemental materials, exact generic CRAH SKU and procurement allocation |
An observed OEM specification does not make the decision to install that equipment an observed campus inventory. Selected assumptions carry no empirical evidence grade; their design-derived descendants remain conditional.
3. Modular capacity and residual treatment
The usable full-module IT design load is 64 × 0.140 MW / (1 − 0.05) = 9.431578947 MW, including 8.96 MW compute-rack load and 0.471578947 MW external IT. The device population of the latter remains unknown; RD030's support rack purchases are not copied.
1000 / 9.431578947 = 106.026785714 module equivalents of demand require ceil(106.026785714) = 107 complete installed facility modules. After 106 full occupied modules, the final module carries 0.252631579 MW IT. The installed modules provision 1009.178947 MW IT and 6848 rack positions. Their unused 9.178947 MW is headroom; the preserved compute demand remains 6785.714286 rack equivalents and the reference remains 1 GW IT.
Every installed count derives from per-module equipment × 107, or per-campus- station equipment × six. Nameplate, contingency-surviving usable capacity and operating draw are retained separately. Serial transformers, UPS and PDUs cannot be summed as additional IT capability.
4. Connected electrical plant
The selected normal path is 230 kV AC utility interface → six campus 230/34.5 kV substations → module MV delivery → 34.5/0.48 kV stepdowns → 480 V main boards and UPS → dual-input STS → 480/415 V transformer PDUs → 415 V busway and shelf whips → existing Supermicro AC/DC shelves → 50 V DC compute bus. Four IT source trains each contain two 2 MW/2 MVA UPS units. The sixteen PDU alternate-source assignments move the four lost-train loads among survivors in a 2/1/1 pattern. Tests examine each complete-train outage against UPS, switchboard, transformer and branch limits including selected losses and power factors.
Facility critical cooling/control has two generic 540 kW UPS sources, one 800 A dual-input STS and a common critical panel. Its concurrent duty is 416.2 kW/module: four CDUs, sixteen CRAH fans, three 45 kW pump allowances and controls. A separate common 4000 A mechanical transfer/distribution assembly feeds every chiller branch from either facility board. Compressors are outside the critical UPS; the thermal buffer bridges their restart.
Six campus stations each contain four 84 MVA transformers, with three surviving after one transformer outage. This is 2016 MVA installed and 1512 MVA selected firm campus transformation, with at most eighteen modules per station. A whole-station outage is a different contingency and has no silent spare. Aggregate facility/campus power factor is selected separately from the Trinergy input-power-factor specification. The selected minimum aggregate facility/campus power factor is 0.95. Margins are narrow at full block: the worst surviving facility board is approximately 3987 A against 4000 A, and an eighteen-block station requires approximately 238.634 MW against 239.4 MW firm at that power factor. Staging, battery-charge limits, actual parasitic curves and duty/ambient acceptance are material gates; all spare equipment or all chiller nameplates cannot run at maximum together.
STS/PDU, shared critical panel and mechanical transfer outputs retain N component paths. Upstream source capacity redundancy does not establish end-to-end fault tolerance or Tier certification. Protection, grounding, fault duty, shelf hold-up, inrush, transfer and battery-recharge acceptance remain engineering gates.
5. Installed equipment BOM
These quantities belong to Reference Plant 01's selected topology. The full canonical BOM (repository-only reference) retains each count derivation, plant and assumption IDs, ratings, redundancy, source claims and product-match status. B2/B3 below identify incremental equipment scopes; the standard's cumulative boundaries are preserved in explicit reconciliations.
| Equipment | Per module or station | Installed at 1 GW IT | Selected specification / limit | Scope |
|---|---|---|---|---|
| Campus substations | 1/station | 6 | 230/34.5 kV; no whole-station spare | B3 |
| Major transformers | 4/station | 24 | 84 MVA each; N+1 per station | B3 |
| HV ring-bus breaker positions | 6/station | 36 | Two line plus four transformer circuits; detailed protection open | B3 |
| Station protection/SCADA/control-DC packages | 1/station | 6 | Nested bay/transformer protection; relay/CT/VT/station battery BOM open | B3 |
| MV outgoing / incomer / tie panels | 6/module; 4/station; 4/station | 642 / 24 / 24 | Selected segmented MV distribution | B3 |
| IT / facility stepdown transformers | 4 / 2 | 428 / 214 | 5 / 3.5 MVA; 34.5/0.48 kV | B2 |
| IT / facility main switchboards | 4 / 2 | 428 / 214 | 5000 / 4000 A at 480 V | B2 |
| IT / facility critical UPS units | 8 / 2 | 856 / 214 | Trinergy 2 MW; generic 540 kW facility class | B2 |
| IT PDU-source STS | 16 | 1712 | 1600 A, 480 V, dual input / N output | B2 |
| Critical STS / critical panel / chiller transfer assembly | 1 / 1 / 1 | 107 each | 800 A / 800 A / 4000 A | B2 |
| Transformer PDUs | 16 | 1712 | 1 MVA, 480→415 V | B2 |
| Busway rails | 32 | 3424 | 800 A, 415 V; selected 12 m each | B2 |
| Shelf-position taps/whips | 512 | 54784 | 60 A; selected 3 m each; equipped positions | B2 |
| External-IT distribution panels | 8 | 856 | Selected 100 kVA; device population unknown | B2 |
| Utility/generator transfer assemblies | 6 | 642 | Four IT and two facility source paths | B2 |
| Standby diesel generator classes / fuel systems | 6 / 6 | 642 each | 4 MW gross/3.9 MW provisional net; exact LV SKU/fuel design open | B3 |
| IT / facility Li5 LFP battery cabinets | 72 / 6 | 7704 / 642 | 31.1 kWh nominal DC; 18 nested modules/cabinet | B2 |
| XDU2300 CDUs | 8 | 856 | 2.3 MWth at 4°C approach; one duty plus one whole-unit spare/POD | B2 |
| Generic warm-water CRAHs | 20 | 2140 | ≥200 kW net sensible each; four duty plus one spare/POD | B2 |
| External facility pumps | 4 | 428 | Three duty + one spare; 450 m³/h, 250 kPa, 45 kW motor | B2 |
| FH3145 dry/free-cooling chiller proxies | 10 | 1070 | 1.606 MWth at declared climate/fluid duty; four duty + one spare per pair | B2 |
| Stratified thermal-buffer tanks | 2 | 214 | 50 m³ each; 80% effective volume selected | B2 |
| Primary / secondary pipe-run allowances | 2 / 8 | 214 / 856 | 200 / 30 m per run; final materials/sections/routes open | B2 |
| Closed-loop treatment skids / cooling control panels | 1 / 1 | 107 each | Functional assemblies; detailed SKU/duty open | B2 |
The geometric allowances yield 41,088 m busway, 164,352 m shelf-whip assemblies, 42,800 m primary pipe and 25,680 m secondary pipe. They are selected dimensions, not measured building routes. Metal, sections, insulation, fittings and complete circuit schedules remain necessary for materials. Cold-plate/manifold assemblies and structural/building quantities remain unresolved. CDU heat exchangers and internal pumps are integrated functions; they are not duplicated as additional standalone installed units.
The 8346 battery cabinets contain 150228 nested modules. Cabinet count is derived from ceil(P_AC/(0.95×263 kW)): nine per IT UPS and three per facility UPS. Nominal DC energy is 2.4258 MWh/module, distinct from the five-minute 1.423333 MWh total AC requirement at installed inverter ratings. The exact IT battery voltage/rating match is supported; the facility bank remains a proxy pending its UPS interface, parallel-bank and runtime acceptance.
6. Thermal architecture and interruption continuity
Select 78% liquid capture of Supermicro rack AC input, with all extra IT air cooled. Thus 0.95×0.78×1000 = 741 MWth enters the liquid branch and 259 MWth enters the air branch. RD030's reported 78% describes its whole DGX/support mixture; it is not an observed Supermicro-rack coefficient. This explicit conservative adaptation gives 74.1% whole-plant liquid capture.
Liquid heat travels cold plate → rack manifold → POD secondary loop → external CDU → common sectionalized facility header → chiller evaporator → condenser/free-cooling coils → environment. Residual room air passes through the warm-water CRAH coils into that same primary heat-transport system. Select 18.9/27.8°C facility supply/return and 22.9/31.8°C secondary supply/return. The primary fluid is EG30, replacing RD030 PG30 to match the inspected US FH3145 functional proxy. Its 460 V rating requires acceptance on 480 V service. The 35°C design point exceeds the captured historical Dulles 0.4% 34.17°C value; contemporary extreme-weather validation remains unknown.
Each full module has 18.4 MWth installed CDU capacity and 9.2 MWth single-duty-per-POD capacity. The sixteen duty CRAHs provide 3.2 MWth selected net sensible capacity, with N+1 within each POD. One failure per POD is covered; arbitrary two failures within a POD are not. Net room duty excludes CRAH fan heat; the gross coil heat sent onward includes that fan heat. The present campus duties are approximately 308.021 MWth net room and 316.581 MWth gross coil heat. Eight duty chillers provide 12.848 MWth evaporator capacity/module. Three duty facility pumps provide 1350 m³/h and 12.6825 MWth transport at the selected 8.9 K rise and 3.8 MJ/m³/K volumetric heat capacity. Full-module and contingency tests compare actual selected heat duties with these capacities, rather than only checking campus-wide nameplate totals.
Two 50 m³ stratified tanks store 2.7056 GJ effective cold capacity/module under the 80% usable-volume selection. At 180 seconds this supports at most 15.031 MWth/module. Generator transfer and staged chiller restart must be accepted within that interval, with critical pumps/CDUs/fans on UPS and spare- start interlocks enforced. A numerical buffer is not proof of actual restart. The XDU2300 August 2026 datasheet is explicitly preliminary development information; product finalization, production availability and qualification remain gates.
7. Power and heat reconciliation
The selected 35°C design-day model uses peak chiller COP 3.8 including condenser fans, four duty CDUs/module at 47.8 kW, sixteen fans at 5 kW, three 45 kW pump budgets and 10 kW controls. Conservative fixed active budgets are retained in the provisioned residual module. Efficiencies are explicit selections: 99.5% IT distribution, 99% PDU, 97% UPS, 99.2% module transformation, 99.7% facility transfer/panel/cable delivery and 99% upstream HV transformation. No selected loss is an observed annual curve.
| Normal grid-powered design-day flow | Approximate result | Boundary / meaning |
|---|---|---|
| IT input | 1000 MW | B1 |
| IT branch including its distribution/UPS/stepdown losses | 1055.014 MW | B2 input branch |
| Protected cooling and controls, before UPS losses | 44.533 MW | B2; inside facility overhead |
| Heat transported through chiller evaporators | 1092.485 MWth | Includes IT plus assigned indoor/loop heat |
| Chiller electricity | 287.496 MW | Selected COP 3.8; annual COP unknown |
| Facility cooling branch including conversion/delivery losses | 337.107 MW | B2 input branch |
| Total B2 facility electrical input / design-day PUE | 1392.121 MW / 1.392121 | At campus 34.5 kV delivery boundary |
| Incremental HV transformation loss | 14.062 MW | B3, outside B2 PUE boundary |
| B3 electrical input | 1406.183 MW | Dedicated upstream campus transformation included |
| Condenser rejection plus direct outdoor/ventilation heat | 1392.121 MWth | Equals B2 input at steady state |
| Total selected B3 heat to environment | 1406.183 MWth | Equals selected B3 input |
The roughly 0.192 difference from legacy PUE 1.20 follows from hot-day refrigeration, conservative operating budgets and electrical losses; the model was not tuned to the old scalar. This peak-versus-historical comparison does not establish an annual PUE contradiction. Annual mode shares, COP, free cooling, weather, part load and load controls remain unknown, so no new annual TWh result replaces 9.4608.
Indoor electrical and air-load heat passes through CRAHs; CDU/primary-pump heat enters the fluid. Compressor/condenser-fan electricity joins outdoor rejected heat. Module transformer loss and approximately 1 MW of facility delivery loss reject outside the chilled loop. The latter requires direct ambient cabinet-room ventilation and acceptable temperatures; any additional fan draw or altered heat path needs qualification and a versioned model change. Serial CDU, header, evaporator and condenser transport are compared, never summed as repeated heat generation. Normal-grid reconciliation excludes standby diesel combustion heat; outage operation requires a separate fuel/heat scenario.
8. Water and materials remain scoped
The selected dry/free-cooling condenser route has no adiabatic spray circuit, cooling tower or intentionally evaporative rejection. Evaporation, drift and tower makeup/blowdown are zero for those absent process subsystems. This does not establish zero whole-site withdrawal or consumption. Circulating EG30/water, initial fill, thermal-buffer inventory, maintenance makeup, leaks, flushing, humidity treatment, domestic use, discharge and usable source/basin returns retain distinct stock/flow semantics. Annual site withdrawal, consumption and make-up remain null; no generic WUE or water/query estimate is imported.
The equipment-to-declaration chain is now explicit, including unsuccessful matches. Carrier's 1.3 MW/4°C CDU declaration is 43.5% below the selected 2.3 MW CDU duty and describes a different product; its 1392 kg dry material inventory cannot be multiplied by XDU2300 counts. The historical 40 MVA transformer, 2500 A/64 m Canalis configuration and unselected Galaxy UPS declarations also remain scoped to their products. Observed UPS/battery assembly weights are not elemental copper, steel or lithium coefficients. No complete material subtotal or tonnes/GW balance is forced. Exact product declarations can be attached later without redesigning the plant or erasing historical candidate evidence.
9. Unknowns, conflicts and delivery gates
All 136 historical unresolved ledger rows remain preserved. They differ from the 47 Run 01 prose research questions, all Critical/High. New unknown-resolution relations (repository-only reference) state whether the selected plant conditionally closes an architectural/count question, partially resolves it or leaves empirical evidence open. No historical unknown is deleted or converted to zero because a different product was selected. Empirical rack heat split, generic equipment qualification, materials, manufacturing yields, supplier capacity/allocation, current climate and annual operation remain distinct from engineering selections. Exact closure counts are retained in the generated unknowns register:
| Historical Run 01 unknown ledger rows | Count | Meaning |
|---|---|---|
| Conditionally resolved by selected design | 20 | Architecture/count layer specified for Reference Plant 01 |
| Partially resolved by selected design | 9 | Some design dimensions specified; remaining blockers retained |
| Unresolved historical rows | 107 | No accepted closure for the selected plant |
| Historical rows retained | 136 | Nothing deleted or overwritten |
| Empirical closures of historical nulls | 0 | Design closure is separate from observed operating/qualified evidence |
Eleven uniquely mapped Critical/High research questions have conditional architecture/count closure: two Critical and nine High. Two further High questions are partially resolved. Their qualification/material/site evidence requirements remain open; these are not eleven empirical confirmations. The current registry also adds 38 selected-design/specification/qualification gaps, for 174 relations in total. Historical ledger-row and prose-question denominators remain separate.
Run 01 conflicts remain. A new append-only classification can identify two valid cooling architectures as design alternatives without overwriting the prior conflict or either claim. The selected busway route avoids the RD030 RPP four-versus-eight count issue; that source inconsistency still exists. The Supermicro 4+4 power-shelf/usable-rack issue remains an acceptance gate. Unrelated semiconductor conflicts receive no opportunistic resolution.
The boundary contract (repository-only reference) stops B2 at campus 34.5 kV delivery and includes selected dedicated campus substations/MV enabling equipment and standby generation in incremental B3. Shared grid generation/transmission and unallocated water works, parcel-specific civil works, fuel volumes, protection and final pipe/conductor specifications remain omitted or unknown, not zero. Site selection, utility connection studies, production qualification, supplier orders, battery/runtime acceptance, environmental/fuel permissions and integrated commissioning tests govern whether this design can become an operating plant. Equipment count establishes neither a procurement reservation nor a delivery date.
10. Reproduce and review
Use the existing standard-library instrument and explicit snapshots:
python -m unittest discover -s tests -v
python scripts/reproduce.py
python scripts/reproduce_run015.py
python -m mbi plant --plant PLANT-GB300-1GW-2026Q4-A --snapshot SNAP-RUN015
python -m mbi balance --snapshot SNAP-RUN00
python -m mbi balance --snapshot SNAP-RUN01-REVIEWED
python -m mbi trace R15-FACILITY-INPUT
The complete suite passes 146 tests, and the selected plant passes 114 engineering checks. All 674 historical entities, three historical snapshot balances and 88 captured-source hashes pass preservation checks. See the independent review (repository-only reference), test log (repository-only reference), equipment BOM (repository-only reference), reconciliation (repository-only reference) and reproduction manifest (repository-only reference).
Verification covers historical entity/balance preservation, source hashes, count derivations, snapshot scope, classification/provenance, electrical train and branch contingencies, apparent-versus-active ratings, net/gross cooling duties, hydraulic and thermal-buffer capacity, power/heat conservation, annual unknown propagation and water semantics. Those checks establish internal accounting consistency for the selected design. Exact equipment compatibility, protection, construction drawings, procurement and commissioning remain the stated empirical/engineering gates.
Source details
Archived Run 01-03 research. These statements retain their time-of-writing context; current material estimates use Run 04. Web prose uses current site terminology; downloadable records preserve original wording. Hashes identify the downloadable records.
Source: RUN_015_FINDINGS.md
SHA-256: 6bcf132901c7e5209db1968d9ad860f8087fb3084c1378d31f7955024be2ec7b
Download research file
Optional: tell Sid you’re reading
The document is open; sharing your name/email is optional.